|
| | |
 |
Method Name: |
 |
Technical logging |
 |
| | |
|
| | |
 |
Method Type: |
|
Borehole Methods
|
 |
| | |
|
 |
 |
Assigned Problems: |
|
 |
 |
|
| | |
 |
Principle: |
|
Technical logs mainly support the analysis and interpretation of other logs or serve for checking the quality of the borehole and casing.
- Caliper log: Records the borehole diameter; changes in borehole diameter are related to well construction, such as casing or drill-bit size, and to fracturing or caving along the borehole wall.
- Cement bond log (CBL) / Acoustic cement bond log (ACBL): Testing the casing-cement-formation bond (interpretation of seismic-wave amplitudes)
- Temperature log: Records the temperature
- Borehole deviation / Directional log / Directional survey: Measurements of direction and inclination of a borehole (determination of borehole geometry)
- Other techniques: Multifinger-caliper log: High-resolution measurements of the borehole cross-section
- Casing collar log: Location and control of casing collars
|
 |
| | |
|
| | |
 |
Keywords: |
|
Temperature; temperature gradient; caliper; diameter; casing; deviation; orientation |
 |
| | |
|
| | |
 |
Prerequisites: |
|
Temperature log should be usually measured as first log and downwards |
 |
| | |
|
| | |
 |
Resolution: |
|
Temperature log: Relative accuracy: 0.01 to 0.1 K; absolute accuracy 1 K or better
Caliper log: Absolute accuracy 1 mm
|
 |
| | |
|
| | |
 |
Expected Results: |
|
- Measured parameter: Caliper log: Positions of one or several arms/ borehole diameter in cm; Temperature log: Temperature in °K or °C, gradient of temperature [K/m]; Cement bond log: Amplitudes of ultra-sonic waves; Borehole deviation: North-South / East-West deviation from the vertical / intended borehole direction in m
- Data analysis: Logs: Measured parameter vs. depth in m
- Interpretation: Geothermal gradient
|
 |
| | |
|
| | |
 |
Combination with other Methods: |
|
- Required additional information: NA
- Usefull additional information: NA
- Independent additional information: NA
|
 |
| | |
|
| | |
 |
Operating Expense: |
|
- Crew size: 1 - 2 persons
- Acquisition speed: see ""Parameter to specify""
- Processing: low
- Equipment rental costs: high
|
 |
| | |
|
| | |
 |
Parameters to specify: |
|
- Instrument type
- Logging speed (4 - 8 m / min)
- Logging speed temperature logging: normally less than 6 m / min
- Diameter or radius for each caliper arm
|
 |
| | |
|
| | |
 |
QC Documents: |
|
- Calibration data: last shop-calibration or on-site calibration
- Around 20 m of repeated measurements
- Borehole information (i.e., casing (type and length), diameter, deviation, fluid properties)
- Complete headers
- Field notes (e.g., all activities, effective time schedule, present personnel)
|
 |
| | |
|
| | |
 |
Products: |
|
- Field logs (displayed using specified scales)
- Composite logs
- Interpretation
|
 |
 |